Module 4 · 30 min

Working with design and engineering

Write specs that invite pushback, treat estimates as ranges, and make tradeoffs out loud with the people who build.

The idea

Once an idea passes its cheap tests, someone has to build it. Non-builders often hand over either a vague wish ("make it like Amazon") or a 40-page document that dictates every pixel. Both fail. The wish leaves builders guessing. The giant spec leaves no room for a better, cheaper way.

The better pattern is to be precise about the problem and the limits, and loose about the solution. Say who it's for, what must be true when it's done, how much time it's worth, and what is out of scope. Then invite the people closest to the materials to shape the how. Designers know what users will misread. Engineers know which "small" change touches a fragile system.

Estimates deserve special care. People are reliably optimistic about their own work. That's a well-documented bias, not laziness. Ask for ranges, not single numbers. Better still, fix the time you'll spend and let scope flex.

Speaking design and engineering doesn't mean learning to code. It means asking good questions, understanding the tradeoffs, and not punishing people for telling you bad news early.

Frameworks

Shaping and appetite

From Ryan Singer's Shape Up, written about how Basecamp works. Before work is handed to a team, it is "shaped": the problem is defined, a rough solution is sketched at low fidelity, risky unknowns ("rabbit holes") are called out, and things that are explicitly out of scope ("no-gos") are listed. Crucially, it has an appetite: how much time this problem is worth, such as two weeks or six. The time is fixed and the scope flexes to fit, the reverse of the usual estimate-then-slip pattern.

When it breaks: Shape Up is one small software company's experience report, not a study. It assumes builders get uninterrupted weeks. Where they also fight fires, protect the time first or the appetite is fiction.

The planning fallacy and reference-class forecasting

In a classic study, Buehler, Griffin and Ross (1994) asked students when they'd finish their senior theses. The average prediction was about 34 days. The actual average was about 56. Even their "worst case" guesses were too optimistic. This planning fallacy is one of the most replicated findings in judgment research. The standard fix, from Kahneman and others, is the "outside view": look at how long similar past projects actually took (the reference class), then adjust.

When it breaks: you need a reference class. For truly novel work, there may be no good comparison. Then use the widest honest range and plan a checkpoint to re-estimate.

The cone of uncertainty

Steve McConnell's Software Estimation popularized the idea that estimates are very uncertain at the start of a project and narrow as decisions get made. Early estimates may be off by several times in either direction. The practical lesson is to ask for ranges, re-estimate at milestones, and not lock budgets to a first guess. Note that the cone's exact proportions are contested. Critics argue the original data was thin and that uncertainty doesn't narrow on its own unless teams actively resolve unknowns. Use it as a picture of the principle, not as a formula.

When it breaks: if decisions keep getting reopened, uncertainty stays wide no matter how far along you are.

The one-page spec

A practical format, not a research finding, that combines the above: problem and outcome, who it's for, the evidence so far, appetite, must-haves, nice-to-haves, no-gos, known risks, and open questions for design and engineering. Short enough that people read it. Specific enough to argue with.

When it breaks: regulated or safety-critical work, such as gas equipment, may need fuller documentation. Keep the one-pager as the front page.

Ridgeline case

The gate-code feature passed its tests in Module 3. Ridgeline has two in-house developers and an outside agency that maintains the app.

The head of growth's first draft said: "Add gate codes to the app and show them to drivers." The lead developer, Tomás, asked three questions. Where does the driver see it, since drivers use the old dispatch tablets, not the app? Who can see the codes, given they're security information? What happens when a customer changes a code the morning of a delivery?

The revised one-page spec:

Tomás's first estimate was "two weeks." Dev Patel asked how long the last two integrations with the dispatch system actually took. The answers were five and seven weeks. The team kept the four-week appetite and cut scope instead: no code-change history in version one. A tradeoff made in the open, before anyone was late.

AI Lab

Goal: turn a solution from your own work into a one-page spec, then stress-test it from the builders' side.

  1. Paste this prompt with your details:
Help me write a one-page spec for this solution: [solution]. It addresses [customer need] toward [outcome]. Evidence so far: [what your tests showed]. Appetite: [time we're willing to spend]. Team: [who will build it].

Use these headings: Problem and outcome; Who it's for; Evidence; Appetite; Must-haves; Nice-to-haves; No-gos; Risks and rabbit holes; Open questions for design; Open questions for engineering.

Keep it under 400 words. Be precise about the problem and loose about the solution.
  1. Then ask the AI to switch roles:
Now act as a skeptical senior engineer and then a skeptical product designer reviewing this spec. Each of you: list the 5 questions you'd ask before agreeing to the appetite, the riskiest hidden assumption, and one way to cut scope without losing the outcome. Don't be polite. Be specific.
  1. Check the output. Look for these issues:
  1. Take the real questions to a real designer or engineer. The AI role-play is rehearsal, not a substitute.

Check yourself

  1. What is an "appetite," and how does it differ from an estimate?
  2. Name the bias behind most late projects and one evidence-based way to counter it.
  3. Why should a spec be precise about the problem but loose about the solution?

Answers

  1. An appetite is how much time a problem is worth to you, set before work starts. An estimate predicts how long a given solution will take. With an appetite, time is fixed and scope flexes.
  2. The planning fallacy. Counter it with reference-class forecasting: check how long similar past work actually took.
  3. Builders often know cheaper or better ways to solve the problem. A fixed solution blocks those ideas, while a clear problem lets them help.